Saw-cut bridge deck being removed over the California Aqueduct
OCSS · Hesperia, CA

Ranchero Road Aqueduct Bridge

Bridge removal and cofferdam plan over the California Aqueduct for Beador Construction, including underwater saw cutting and pier removal.

Services provided
Bridge demolitionCofferdamRemoval sequence
Crane lifting a full steel truss bridge span out of a rocky creek canyon
OCSS · Santa Barbara County

East Mountain Drive Bridge

Bridge removal and crane pick plan to lift out the full 35-kip steel truss span in one piece, for Papich Construction.

Services provided
Bridge removalCrane pick planRigging
Timber falsework bents on steel beams supporting a cast-in-place bridge deck
OCSS · California High-Speed Rail

Avenue 24 Underpass

Falsework design for a cast-in-place deck for Papich Construction, plus field inspection and certification of the built falsework before the pour.

Services provided
Falsework designField inspectionPour certification
Slide rail shoring system in a deep excavation beside a new steel-frame hospital building
OCSS · Irvine

Hoag Hospital Irvine

Slide rail excavation and shoring plan for an underground storage tank installation at the Phase 1C hospital expansion, for Murray Company with Trench Shoring Co.

Services provided
Slide rail shoringExcavation plan
New wood roof trusses over a 21,000 square foot community building during reconstruction
OCSS · Lake Forest

Forest Gardens Community Building

Emergency roof repair for a 21,000 sq ft banquet hall: temporary vertical shoring, damaged truss replacement and structural details.

Services provided
Emergency repairTruss replacementTemporary shoring
Framed and sheathed two-story custom home in Newport Beach
OCSS · Newport Beach

20141 Spruce Avenue Residence

Full structural design for a new custom home: foundation and anchorage, shear walls and hold-downs, and floor and roof framing.

Services provided
Foundation designShear wallsFraming design
Soldier pile and steel plate lagging shoring at a bridge abutment
OCSS · I-10 Express Lanes

Day Canyon Channel Bridge

Excavation and shoring plan for the abutment and bent foundations, using steel soldier piles with steel plate lagging, for the Flatiron/Myers joint venture.

Services provided
Soldier pile shoringSteel plate lagging
Timber jacking bent with steel caps under the girders of an existing freeway overcrossing
OCSS · Caltrans District 8

Cima Road Overcrossing

Temporary jacking bents to support and lift the existing steel girders, sized for 100-kip girder reactions, for Beador Construction.

Services provided
Jacking bentsTemporary supports
Shoring towers under an elevated concrete deck at the new San Diego airport terminal
OCSS · San Diego International Airport

New Terminal 1

Independent field inspection of 24 temporary structures across the new terminal and parking plaza, from shoring and stair towers to scaffolding and a construction hoist.

Services provided
Temporary structure inspectionThird-party review
Temporary cantilever pile wall supporting a construction access ramp
OCSS · Santa Barbara

UCSB Stadium Road Ramp

Temporary cantilever pile and lagging wall to support a built-up construction access ramp for Papich Construction, designed into sandstone with equipment surcharge.

Services provided
Cantilever pile wallTemporary retaining
OCSS truck on site as a crane lifts a 1921 steel truss span
OCSS · Monterey County

Nacimiento Lake Drive Bridge

Bridge demolition plan and crane pick to remove the 1921 steel truss over the San Antonio River.

Services provided
Bridge demolitionCrane pick
Braced steel jacking pit with walers
OCSS · SR-57 / SR-60 Interchange

SR-57/SR-60 Jacking Pit

Braced excavation design for a jacking pit at the SR-57/SR-60 interchange.

Services provided
Braced excavationJacking pit
Slide rail shoring for a water storage installation alongside the I-5 freeway
OCSS · I-5 Corridor

I-5 Water Storage Shoring

Slide rail shoring for a water storage installation alongside the active I-5 freeway.

Services provided
Slide rail shoringFreeway-adjacent
Slide rail shoring pit in soft, wet soil
OCSS · Orange County

Slide Rail Shoring Pit

Slide rail shoring designed with Trench Shoring Co. for Griffith Co. in soft, wet soils where trench shields weren't feasible.

Services provided
Slide rail shoringSoft soils
Timber and steel soundwall framing above K-rail on Rodeo Drive
OCSS · Beverly Hills

319 N. Rodeo Drive

Sidewalk canopy and soundwall design for a new four-story retail building on Rodeo Drive.

Services provided
Sidewalk canopySoundwall